Turnout 20 – Day 8

Turnout 20 – Day 8

First major project is now nearly complete, with the deck at Wensley crossing in, leveled and secured. Just need to replace the tarmac edges and then re-paint the road markings.     Please Donate...
Turnout 20 – Day 7

Turnout 20 – Day 7

Upgrading the railway is a 7 day a week job. The installation of the new road deck at Wensley has been the focus for today, and hopefully by now the deck is installed and fixed down. Next staep wil  be to replace the tarmac on either side.      Please Donate...
Turnout 20 – Day 6

Turnout 20 – Day 6

the weekend is already apon us and progress so far has been good. The rail has arrived for Harmby, the crossing at Wensley has been dug out, new track laid and the decking supports are in. Swale bridge is being re-timbered, with all the timber we require having been...
Turnout 20 – Day 5

Turnout 20 – Day 5

Focus today has been back with Wensley crossing where the track has been replaced and now the new road deck is being installed. This is requireing concrete shouldsers to be created as supports for the edge beams that will then support the deck panels. The position and...
Turnout 20 – Day 4

Turnout 20 – Day 4

In addition to the 3 major projects at Harmby, Wensley and Swale bridge, the Army are also helpig out with some smaller projects to both practice their skills and benefit the railway. One of these is to carry out geotechnical surveys of a number of strecthes of the...