First Works Train
The first train to run over the railway ran on the 23rd September, taking materials to one of our works sites in preparation for the Infrastructure Upgrade. The class 03 took a number of wagons, including the recently refurbished Shark ballast plough from Leeming to...
Sleepers Arrive
With the recovery of the required sleepers for the Harmby re-lay part of the project complete, they have now been transported to our infrastructure railhead. This was no mean task with over 750 sleepers needing to be moved and made ready for re-use. We are now in the...