by | | Infrastructure Upgrade
Focus today has been back with Wensley crossing where the track has been replaced and now the new road deck is being installed. This is requireing concrete shouldsers to be created as supports for the edge beams that will then support the deck panels. The position and...
by | | Infrastructure Upgrade
In addition to the 3 major projects at Harmby, Wensley and Swale bridge, the Army are also helpig out with some smaller projects to both practice their skills and benefit the railway. One of these is to carry out geotechnical surveys of a number of strecthes of the...
by | | Infrastructure Upgrade
The third major project in Exercise Turnout 20 is the re-timbering of Swale bridge. This requires the wooden beans under the sleepers and rails to be replaced with new timbers. While this is happening we are also goign to repair some of the handrails and walking...
by | | Infrastructure Upgrade
With the rail for the Harmby Relay project now deposited at Leyburn, we can turn our focus to the renewal of the crossing deck at Wensley. To date the Railway has upgraded nearly all of our road crossings to use modern decking components, with Wensley left as one of...
by | | Infrastructure Upgrade
Exercise Turnout 20 is now in progress, with work due to take place at Harmby, Wensley and Swale Bridge amongst other locations. The Harmby portion is to relay 500 yards of track with flat bottom rail on concrete sleepers, and to achieve that we needed a source of...