Turnout 20 – Day 9
More progres at Wensley with the tidying up of the areas around the crossing and compacting the crushed stone that will be under the new tarmac. Tarmac to be laid tomorrow and will see this job finished. Elsewhere the track re-lay at Harmby is progressing, hopefully...
Turnout 20 – Day 8
First major project is now nearly complete, with the deck at Wensley crossing in, leveled and secured. Just need to replace the tarmac edges and then re-paint the road markings.
Turnout 20 – Day 7
Upgrading the railway is a 7 day a week job. The installation of the new road deck at Wensley has been the focus for today, and hopefully by now the deck is installed and fixed down. Next staep wil be to replace the tarmac on either side. Wensley...
Turnout 20 – Day 6
the weekend is already apon us and progress so far has been good. The rail has arrived for Harmby, the crossing at Wensley has been dug out, new track laid and the decking supports are in. Swale bridge is being re-timbered, with all the timber we require having been...
Turnout 20 – Day 5
Focus today has been back with Wensley crossing where the track has been replaced and now the new road deck is being installed. This is requireing concrete shouldsers to be created as supports for the edge beams that will then support the deck panels. The position and...
Turnout 20 – Day 4
In addition to the 3 major projects at Harmby, Wensley and Swale bridge, the Army are also helpig out with some smaller projects to both practice their skills and benefit the railway. One of these is to carry out geotechnical surveys of a number of strecthes of the...
Turnout 20 – Day 3
The third major project in Exercise Turnout 20 is the re-timbering of Swale bridge. This requires the wooden beans under the sleepers and rails to be replaced with new timbers. While this is happening we are also goign to repair some of the handrails and walking...
Turnout 20 – Day 2
With the rail for the Harmby Relay project now deposited at Leyburn, we can turn our focus to the renewal of the crossing deck at Wensley. To date the Railway has upgraded nearly all of our road crossings to use modern decking components, with Wensley left as one of...
Turnout 20 – Day 1
Exercise Turnout 20 is now in progress, with work due to take place at Harmby, Wensley and Swale Bridge amongst other locations. The Harmby portion is to relay 500 yards of track with flat bottom rail on concrete sleepers, and to achieve that we needed a source of...
Turnout 20 Day -1
Excercise Turnout 20 is really starting to gain momentum now. More heavy equipment has been deliverd to the main railhead and the first works train has been assemebed for use by the Army. Monday will be the first official day of the exercise, with the arrival to the...
Exercise Turnout 20
We are pleased to announce that the Wensleydale Railway are getting some assistance in the major infrasturcure upgrade project. The British Army, in the shape of 507 Specialist Team Royal Engineers (STRE). They have been helping us plan the project for aome months...
First Works Train
The first train to run over the railway ran on the 23rd September, taking materials to one of our works sites in preparation for the Infrastructure Upgrade. The class 03 took a number of wagons, including the recently refurbished Shark ballast plough from Leeming to...
Sleepers Arrive
With the recovery of the required sleepers for the Harmby re-lay part of the project complete, they have now been transported to our infrastructure railhead. This was no mean task with over 750 sleepers needing to be moved and made ready for re-use. We are now in the...
Sleeper Recovery
The first major task of the Infrastructure Upgrade project was to obtain suitable concrete sleepers to be used on the track relay at Harmby. A search for the 'Goldilocks' sleepers was carried out. They needed to be in good condition, not too far away, not too dificult...
AGM 2020
The Chairman and Board of Wensleydale Railway plc intend to hold a remote AGM by Zoom on Monday 28th September at 18:00hrs. https://zoom.us/j/95665384060?pwd=V1p6djNxTHA1QUF1RVY3NG0vWkJxUT09 Meeting ID: 956 6538 4060 Passcode: 114316
Coach Restoration
While most of the focus over the last few months has been on the Leeming Bar station house, a dedicated team have been working away in the Maintenece Shed refurbishing some of our coaching stock ready for Polar Express. Mk2 TSO 5378 has been stripped and a number of...
Work continues on Leeming Bar Station House
Even with the railway closed and our staff off site due to Coronavirus, our building contractor has arranged a safe method of working to allow them to progress the redevelopment of the main building. Work on stripping the building has now been completed, and most of...
Thanks Total !
When things are tough its our friends who can really make a big difference, and we can count on Total UK as a great friend. Total have featured the railway in their corporate news and community awareness section of their web site, following their generous support of...
Turnout 20 – Day 9
More progres at Wensley with the tidying up of the areas around the crossing and compacting the crushed stone that will be under the new tarmac. Tarmac to be laid tomorrow and will see this job finished. Elsewhere the track re-lay at Harmby is progressing, hopefully...
Turnout 20 – Day 8
First major project is now nearly complete, with the deck at Wensley crossing in, leveled and secured. Just need to replace the tarmac edges and then re-paint the road markings.
Turnout 20 – Day 7
Upgrading the railway is a 7 day a week job. The installation of the new road deck at Wensley has been the focus for today, and hopefully by now the deck is installed and fixed down. Next staep wil be to replace the tarmac on either side. Wensley...
Turnout 20 – Day 6
the weekend is already apon us and progress so far has been good. The rail has arrived for Harmby, the crossing at Wensley has been dug out, new track laid and the decking supports are in. Swale bridge is being re-timbered, with all the timber we require having been...
Turnout 20 – Day 5
Focus today has been back with Wensley crossing where the track has been replaced and now the new road deck is being installed. This is requireing concrete shouldsers to be created as supports for the edge beams that will then support the deck panels. The position and...
Turnout 20 – Day 4
In addition to the 3 major projects at Harmby, Wensley and Swale bridge, the Army are also helpig out with some smaller projects to both practice their skills and benefit the railway. One of these is to carry out geotechnical surveys of a number of strecthes of the...
Turnout 20 – Day 3
The third major project in Exercise Turnout 20 is the re-timbering of Swale bridge. This requires the wooden beans under the sleepers and rails to be replaced with new timbers. While this is happening we are also goign to repair some of the handrails and walking...
Turnout 20 – Day 2
With the rail for the Harmby Relay project now deposited at Leyburn, we can turn our focus to the renewal of the crossing deck at Wensley. To date the Railway has upgraded nearly all of our road crossings to use modern decking components, with Wensley left as one of...
Turnout 20 – Day 1
Exercise Turnout 20 is now in progress, with work due to take place at Harmby, Wensley and Swale Bridge amongst other locations. The Harmby portion is to relay 500 yards of track with flat bottom rail on concrete sleepers, and to achieve that we needed a source of...
Turnout 20 Day -1
Excercise Turnout 20 is really starting to gain momentum now. More heavy equipment has been deliverd to the main railhead and the first works train has been assemebed for use by the Army. Monday will be the first official day of the exercise, with the arrival to the...
Exercise Turnout 20
We are pleased to announce that the Wensleydale Railway are getting some assistance in the major infrasturcure upgrade project. The British Army, in the shape of 507 Specialist Team Royal Engineers (STRE). They have been helping us plan the project for aome months...
First Works Train
The first train to run over the railway ran on the 23rd September, taking materials to one of our works sites in preparation for the Infrastructure Upgrade. The class 03 took a number of wagons, including the recently refurbished Shark ballast plough from Leeming to...
Sleepers Arrive
With the recovery of the required sleepers for the Harmby re-lay part of the project complete, they have now been transported to our infrastructure railhead. This was no mean task with over 750 sleepers needing to be moved and made ready for re-use. We are now in the...
Sleeper Recovery
The first major task of the Infrastructure Upgrade project was to obtain suitable concrete sleepers to be used on the track relay at Harmby. A search for the 'Goldilocks' sleepers was carried out. They needed to be in good condition, not too far away, not too dificult...
AGM 2020
The Chairman and Board of Wensleydale Railway plc intend to hold a remote AGM by Zoom on Monday 28th September at 18:00hrs. https://zoom.us/j/95665384060?pwd=V1p6djNxTHA1QUF1RVY3NG0vWkJxUT09 Meeting ID: 956 6538 4060 Passcode: 114316
Coach Restoration
While most of the focus over the last few months has been on the Leeming Bar station house, a dedicated team have been working away in the Maintenece Shed refurbishing some of our coaching stock ready for Polar Express. Mk2 TSO 5378 has been stripped and a number of...
Work continues on Leeming Bar Station House
Even with the railway closed and our staff off site due to Coronavirus, our building contractor has arranged a safe method of working to allow them to progress the redevelopment of the main building. Work on stripping the building has now been completed, and most of...
Thanks Total !
When things are tough its our friends who can really make a big difference, and we can count on Total UK as a great friend. Total have featured the railway in their corporate news and community awareness section of their web site, following their generous support of...